CHURCH BUILDING: Work continues on our church roof. Contractors are removing the old decking and replacing it with new 3/4-inch tongue-and-groove plywood, and then, installing ice and water shield underlayment. To date, the area over the sacristy and altar is 100% complete. The area over the western half of the main roof is also 100 % complete. The area over the east side of the main roof is 50% complete. Work next week will be focused on completion of the entire main roof with ice and water shield and the start of work for installing the slate shingles, copper flashing, and gutters. Work on the roof the steeples will also start. COMMUNITY CENTER: Electrical and HVAC work began Thursday. Sheetrock hanging and texture will begin at some point during the coming week. Please continue to pray for steady progress and good weather. Your patience and cooperation are appreciated.